CAT III AERONATUCICAL GROUND LIGHTING UPGRADE - WCC/Safegate Consortium

CLIENT: Perth Airport Pty Ltd

CONSTRUCTION PERIOD:

  • Commencement January 2016 -

WCC SCOPE OF WORKS:

<1,000No. SIT Pits

<200No. Structural Pits

28Km of Primary Trenching

48Km of Secondary Trenching

3No. x Airfield Lighting Equipment Rooms

Central Strip Asphalt Overlay Runway 03/21

PROGRESS TO DATE: April

13Km of Primary Trenching & Pits